Projects / Madinat Al Mataar / Azizi Venice 5
DLD registered
UNDER CONSTRUCTION

Azizi Venice 5

عزيزى فينيس 5

By Azizi Developments

Madinat Al Mataar

Expected handover Q4 2025

64%COMPLETE

Project facts

DLD project number
2822
Units
484
Buildings
2
Escrow registered
Yes
Start date
13 Oct 2023
Status
Under construction
Planned completion
30 Oct 2025
Project type
Buildings
Zoning authority
Dubai South
Master project
Dubai World Central

Description

RESIDENTIAL & COMMERCIAL (with retails) :Tower A : 3B+G+15+R+TR Tower B : 3B+G+16+R+TR "

Location

Madinat Al Mataar, Dubai

Map preview · Location not verified

Source: Dubai Land Department open data, last updated 1 Nov 2026.