DLD registeredUnder constructionProjects / Al Safouh First / Biltmore Sufouh
BS
DLD registered
UNDER CONSTRUCTION
Biltmore Sufouh
بلتمور صفوح
Al Safouh First
Expected handover Q1 2026
88%COMPLETE
Project facts
- DLD project number
- 2619
- Units
- 477
- Buildings
- 1
- Escrow registered
- Yes
- Start date
- 1 Jun 2022
- Status
- Under construction
- Planned completion
- 29 Jan 2026
- Project type
- Buildings
- Zoning authority
- Dubai Development Authority (DDA)
- Master project
- Sufouh Gardens
- Master developer
- Dham
Description
4B+G+44F+R. Hotel Apartments.The project designed to have a concrete structure and block with internal and external finishes.
Location
Al Safouh First, Dubai
Map preview · Location not verified
Source: Dubai Land Department open data, last updated 1 Nov 2026.